The Volume change page compares two surveys of the same ground. It shows how much was added and how much was removed between them, where the ground went up or down, and, from the weighbridge records, the density of the waste placed in that time.
- In the Surveys list on the left, click From on the older survey, the baseline, and To on the newer one. The page opens on your newest survey and the one before it.
- Under Settings, set Ignore changes under (m). A change smaller than this counts as no change, so that the small differences between two surveys of untouched ground are not counted as earthworks.
- Under Clip to, choose a landfill cell to compare only the ground inside it, or Whole survey. Two surface models are compared over the landfill cells only: choose a cell or All cells.
You can compare two surveys with GPS points, two surface models, or one of each.
- Volume added: where the ground is higher in the newer survey.
- Volume removed: where it is lower.
- Net · added − removed: added minus removed. The line under it says which is larger.
- Overlap: the area both surveys cover, where they can be compared.
- In-place density: the tonnes placed between the two survey dates, divided by the net volume added. See below.
How it is measured. With GPS points, the newer surface is compared with the baseline's wherever both were surveyed. With two surface models, the change is measured on the server from every pixel of the two models inside the cell.
The density comes from the weighbridge records in the Waste module. Topo adds up the loads placed after the baseline date, up to and including the date of the newer survey, and divides them by the net volume added. Both disposed waste and soil reused as cover count, because both take up space. The bar under the figure shows the share of each.
When you clip to a cell, only the loads that name that cell count. A load that names no cell is never shared out between cells. The page says how many tonnes named no cell.
When there is no density, the tile says why:
- No waste placed in this period: no loads were recorded between the two dates.
- No density: the volume fell: more was removed than added.
- Tonnage is not recorded per cell: the site's loads do not name cells, so only the whole site has a density.
- Tonnage is recorded for the whole cell: you clipped to one part of a cell made of several parts. Loads name the cell, not its parts.
The Surface view shows the newer survey in 3D, coloured by change:
- Ground raised in green and Ground lowered in blue. The deeper the colour, the larger the change.
- No change in light grey: changes under the threshold.
- Outside the baseline in dark grey: ground the baseline does not cover.
Point at the surface to read the change at that spot. See The 3D view for how to turn, zoom and light it.
The legend in the corner of the view holds a bar chart, Change · m, of how much of the overlap moved by how much, in the same colours as the surface. The shaded band in the middle is the threshold: drag either edge to change Ignore changes under (m). The line under the chart gives the share of the overlap that counts as no change.
The line at the bottom gives the details for checking: the coordinate system, how many points lie over the baseline (or the pixel size for surface models), the smallest and largest change, and the mean change.
Click Save result at the top right to keep the figures with the two surveys, the threshold and the cell. Save one result for each pair of surveys that follow each other, and the History page charts how each cell filled up.
- Needs two surveys: the site has only one survey with GPS points or a surface model. Add a second one in the Surveys module.
- The two surveys are in different coordinate systems: import one of them again in the same coordinate system as the other.
- Has fewer than three points or has no points in a metric coordinate system: see Volume.
- The two surface models do not overlap inside this cell: choose another cell or All cells.
- Every compared point moved at least … m the same way: the two surveys are probably in different height references, for example heights above the ellipsoid in one and heights above sea level in the other. This is not earthworks. Check how each survey was exported, and import the wrong one again.